Work packages > Work package 1
Start date or starting event: Month 1
Work package title: Project management
Activity Type: MGT
Work Package Leader: CODA-VAR
Participants: CODA-VAR, IAH, CVI, IZSLER, FLI, IIL, LVRI, FUNPRECIT, AFSSA, IVI, KVI, UGLA, DTU, Merial
Objectives
- 1. To coordinate the administrative and financial management of the project
- 2. To organise project management and scientific meetings
- 3. To develop a project website and disseminate results to different stakeholders
Description of work
-
Task 1. Project management (partner 1)
- 1.1. The Project Management Team (PMT)
- 1.2. The Project Coordination Team (PCT)
- 1.3. Executive Board (EB)
- 1.4. The Partner Contact Point (PCP)
- 1.5. The Project Website
- Task 2. Organising Meetings (partner 1)
- Task 3. Dissemination of results (all partners)
- Task 4. Ethical issues (all partners)
- Task 5. Gender aspects (all partners)
Deliverables
- 1.1. Final Consortium Agreement (M1)
- 1.2. Final plan for using and disseminating foreground (M2)
- 1.3. Report on raising public participation and awareness (M2)
- 1.4. A functional project website (M2)
- 1.5. Periodic scientific, ethical and financial report periodic 1 (M18)
- 1.6. Periodic scientific, ethical and financial report periodic 2, final project report and report on "awareness and wider societal implications" (M39)
|